With 29,460 square meters and 6 floors, the INTERXION MAD4 data processing center is the largest in the capital, with a capacity of 34 MW of power and the capacity to store 140,000 servers. The work has a budget of 230 millions.
Core collaborates in the generation of the As-Built model of the diesel installations that are used to cool the servers in the case of a failure